Avaliação do processo de planejamento do setor elétrico brasileiro: estudo de caso para o sistema de transmissão gralha azul

DSpace Repository

A- A A+

Avaliação do processo de planejamento do setor elétrico brasileiro: estudo de caso para o sistema de transmissão gralha azul

Show simple item record

dc.contributor Universidade Federal de Santa Catarina pt_BR
dc.contributor.advisor Rosa, Mauro Augusto da
dc.contributor.author Espíndola, Luan Corrêa
dc.date.accessioned 2022-04-22T13:00:27Z
dc.date.available 2022-04-22T13:00:27Z
dc.date.issued 2022-03-28
dc.identifier.uri https://repositorio.ufsc.br/handle/123456789/234115
dc.description TCC (graduação) - Universidade Federal de Santa Catarina. Centro Tecnológico. Engenharia Elétrica. pt_BR
dc.description.abstract Com o constante crescimento do consumo de energia elétrica e a grande transformação em curso na matriz energética mundial, e em especial no Brasil, o processo de planejamento da expansão da rede de transmissão vem sendo constantemente revisitado. A proliferação de fontes de energia renováveis, não convencionais e de caráter distribuído, bem como novas tecnologias para a transmissão de grandes blocos de potência entre regiões, vêm trazendo novos desafios ao planejamento da expansão da rede elétrica. Neste contexto, o presente trabalho visa enumerar e analisar as etapas do planejamento estabelecidas para uma alternativa de expansão da transmissão na região Centro-Sul do Estado do Paraná, a qual foi posteriormente denominada de Sistema de Transmissão Gralha Azul. Posteriormente, foi verificado se os impactos esperados da entrada em operação dos novos ativos, avaliados na etapa de planejamento, se concretizaram com o sistema efetivamente implementado. Para isso, foi elaborada a evolução cronológica do empreendimento Gralha Azul, desde o processo de planejamento e aprovação do projeto básico até a construção e energização das obras, e realizada a comparação entre os documentos contendo os resultados dos estudos realizados na etapa de planejamento das obras, com os estudos pré-operacionais, documentos contendo os resultados dos estudos realizados para a etapa de energização das obras, considerando os parâmetros das obras como construídas. pt_BR
dc.description.abstract With the constant growth of electrical energy consumption and the big change ongoing in the world energy matrix, especially in Brazil, the power transmission grid expansion planning process has been constantly verified. The proliferation of renewable, unconventional, and distributed energy sources, as well as new technologies for the transmission of large blocks of power between regions, have been bringing new challenges to the expansion planning of the power transmission grid. In this context, the present work aims to enumerate and analyze the planning process established for an alternative of transmission expansion in the Center-South region of Paraná State, which was later called Gralha Azul Transmission System. Then, was verified if the expected impacts of the new assets start-up, evaluated in the planning stage, were achieved with the system effectively implanted. To this end, the chronological evolution of Gralha Azul project was elaborated, from the planning process and approval of basic project to the construction and energization of the project, and a comparison was made between the documents containing the results of the studies carried out in the planning stage, and the preoperational studies, documents containing the results of the studies carried out for energizing stage, considering the as built parameters of the project. pt_BR
dc.format.extent 98 f. pt_BR
dc.language.iso por pt_BR
dc.publisher Florianópolis, SC pt_BR
dc.rights Open Access
dc.subject Planejamento pt_BR
dc.subject Setor elétrico brasileiro pt_BR
dc.subject Sistema de transmissão gralha azul pt_BR
dc.subject Como construído pt_BR
dc.subject Planning pt_BR
dc.subject Brazilian electrical sector pt_BR
dc.subject Gralha azul transmission system pt_BR
dc.subject As built pt_BR
dc.title Avaliação do processo de planejamento do setor elétrico brasileiro: estudo de caso para o sistema de transmissão gralha azul pt_BR
dc.type TCCgrad pt_BR
dc.contributor.advisor-co Skorupa, Thayane


Files in this item

Files Size Format View Description
TCC_Luan_Espindola_assinado.pdf 2.668Mb PDF View/Open TCC

This item appears in the following Collection(s)

Show simple item record

Search DSpace


Browse

My Account

Statistics

Compartilhar