Planejamento das atividades eletromecânicas de usinas fotovoltaicas
Show simple item record
dc.contributor |
Universidade Federal de Santa Catarina |
pt_BR |
dc.contributor.advisor |
Mutti, Cristine do Nascimento |
|
dc.contributor.author |
Nohatto, Mariana Fornara |
|
dc.date.accessioned |
2022-03-22T16:27:37Z |
|
dc.date.available |
2022-03-22T16:27:37Z |
|
dc.date.issued |
2022-03-10 |
|
dc.identifier.uri |
https://repositorio.ufsc.br/handle/123456789/232533 |
|
dc.description |
TCC (graduação) - Universidade Federal de Santa Catarina. Centro Tecnológico. Engenharia Civil. |
pt_BR |
dc.description.abstract |
Ao longo dos últimos dez anos, aumentou significativamente no Brasil a presença de
fontes renováveis em sua matriz energética. Tal fator foi importante para a construção
civil, que passou a atuar no desenvolvimento de parques eólicos e solares. Esse
trabalho tem por objetivo explorar o planejamento de obras, analisando
comparativamente dois modelos de cronograma aplicados a uma usina solar
fotovoltaica: o modelo de diagrama de Gantt e o de linha de Balanceamento. O
trabalho é um estudo de caso, pois os dois modelos foram aplicados no mesmo
empreendimento ao longo do seu período de execução, sendo inicialmente utilizado
o diagrama de Gantt e posteriormente aplicado o planejamento em linha de
Balanceamento. Com a coleta de dados relativos ao avanço físico do projeto e a
alocação da mão de obra e de equipamentos em cada uma das atividades da estrutura
analítica do projeto, foi analisada a aderência ao planejamento nos dois momentos da
obra. Verificou-se que a aplicação da linha de Balanceamento permitiu a identificação
de interferências entre as atividades, permitindo ao planejamento realizar um melhor
sequenciamento entre as atividades e como consequência otimizar o uso dos
recursos. |
pt_BR |
dc.description.abstract |
Over the course of the last ten years, the presence of renewable sources in Brazil's
energy matrix has increased significantly. This factor was important for the construction
industry, which became involved in the development of wind and solar farms. This work
seeks to explore construction planning by comparatively analyzing two schedule
models applied to a photovoltaic plant: the Gantt chart model and the line of balance
model. The work is a case study, because both models were applied in the same
enterprise along its execution period, the Gantt diagram being used initially and the
line of balance planning applied later. With the data collection related to the project's
physical progress and the allocation of manpower and equipment in all activities of the
project's analytical structure, the adherence to planning was analyzed in both moments
of the project. It was verified that the application of the line of balance allowed the
identification of interferences among the activities, allowing the planning to perform a
better sequencing among the activities and consequently optimize the use of
resources. |
pt_BR |
dc.format.extent |
83 f. |
pt_BR |
dc.language.iso |
por |
pt_BR |
dc.publisher |
Florianópolis, SC |
pt_BR |
dc.rights |
Open Access |
|
dc.subject |
Diagrama de Gantt |
pt_BR |
dc.subject |
Usinas Fotovoltaicas |
pt_BR |
dc.subject |
Linha de Balanceamento |
pt_BR |
dc.title |
Planejamento das atividades eletromecânicas de usinas fotovoltaicas |
pt_BR |
dc.type |
TCCgrad |
pt_BR |
Files in this item
This item appears in the following Collection(s)
Show simple item record
Search DSpace
Browse
-
All of DSpace
-
This Collection
My Account
Statistics
Compartilhar